Status: editorial and internal technical QA complete; external review ongoing Written by: Prepared: Reviewer: Waseem Sial, External Reviewer, Engineer External review status: Ongoing review Review scope: Formulas, units, worked examples, sources, and stated limitations Calculator scope: one gravel-filled dry well pit with a uniform rectangular, circular, or known-area cross-section

Gross pit volume

Enter dimensions m³

Effective storage– m³
Storage equivalent– L
Stone order– m³
Measured area– m²
Gross equivalent– L
Void ratio applied–

Gross pit volume = area × pit depth; effective storage = gross pit volume × stone void ratio

Gross volume, storage, and stone order are three separate numbers. The stone order uses the gross volume, because bulk stone ships with its voids already present.

An excavated rectangular dry well pit lined with black geotextile fabric, clean washed gravel being poured from a shovel…
A gravel-filled dry well pit under construction. Measure the pit dimensions on the ground first, then apply the supplier-confirmed void ratio to the gross volume.

A dry well quantity is three numbers, not one. Gross pit volume is the hole you dug. Effective storage is the water space left between the stones. The stone order is the loose bulk stone that fills the hole, voids included.

This calculator keeps those three lines separate for one gravel-filled pit with a uniform cross-section. Enter the pit dimensions and the supplier-confirmed void ratio, and it returns gross volume, storage in gallons or litres, and the stone order. Use the dry well measurement guide to record the field dimensions, the calculation-method guide to check that a gravel pit is the right method for your structure, and the worked dry well example to check a full record.

How much water does a gravel-filled dry well hold?

It holds the gross pit volume multiplied by the stone void ratio. A 6 ft by 6 ft pit that is 5 ft deep holds 180 ft3 of space, but at a void ratio of 0.35 only 63 ft3 of that space is water, or 471.3 gallons. The other 117 ft3 is stone.

Use the result in 3 stages.

Record gross volume first, storage second, and the loose stone order last. Each stage has a different source and can change for a different reason.

ResultCalculationWhat you must confirm
Gross pit volumeMeasured area × pit depthShape, dimensions, depth, and units
Effective storageGross pit volume × stone void ratioExact stone product and supplier-confirmed ratio
Stone orderGross pit volume, rounded up only at the supplier incrementSelling unit, minimum order, and delivery increment

This page covers a stormwater dry well: a pit that receives runoff and lets it soak into the ground. It does not cover a drilled water well, where the volume is a water column in a borehole. If your structure is a water well, this calculator gives the wrong answer.

Which measurements do you need?

You need the pit plan dimensions, the pit depth, and the stone void ratio for the exact product being placed. Measure in the units printed beside the fields and record where each dimension came from.

Length and width

Measure the usable inside limits of the pit at the depth where stone will sit. Excavation width can include working space, side slopes, or overbreak that stone never fills. Split an abrupt width change into a separate section.

Diameter

Measure a circular pit's full width through its centre. A radius is half the diameter, so entering a radius in the diameter field reduces the calculated area to one quarter of the intended circle.

Known area

Use known-area mode when a drawing, survey, or separate shape calculation already gives the pit area. Confirm whether that area includes openings, pipes, or chamber footprints that displace stone before entering it.

Pit depth

Enter the depth of the stone-filled pit, from the top of the stone zone to the pit bottom. A soil cap, chamber lid, or cover above the stone is not part of this depth. Take enough readings to represent the pit, and split the pit where depth changes clearly.

Stone void ratio

Enter the void ratio for the exact stone product and condition, confirmed by the supplier or the project record. Clean washed gravel is typically 0.30 to 0.40. That range is a typical range, not a project value, so the calculator leaves the field blank rather than prefilling a number that could be wrong for your stone. Crushed, dirty, or mixed stone can fall below the clean range, and the ratio choice alone can change storage by about one third on the same pit.

What formulas does the calculator use?

The calculator finds plan area, multiplies by pit depth, and then multiplies the gross volume by the void ratio. It retains full JavaScript precision during the calculation and displays up to 3 decimal places.

Rectangle area = length × width

Circle area = π × (diameter ÷ 2)²

Gross pit volume = area × pit depth

Effective storage = gross pit volume × stone void ratio

Stone order = ceiling(gross pit volume ÷ supplier increment) × supplier increment

When no supplier increment is entered, the stone order stays at the unrounded gross volume. An exact increment multiple stays unchanged.

Displayed conversionRelationshipCalculator use
Cubic feet to cubic yards27 ft³ = 1 yd³Imperial gross volume and stone order
Cubic feet to gallons1 ft³ = 7.48052 galImperial storage equivalent
Cubic metres to litres1 m³ = 1,000 LMetric gross and storage equivalents
Cubic yards to cubic metres1 yd³ = 0.764554857984 m³Checking a supplier unit conversion

NIST Handbook 44 Appendix C supplies the cited volume relationships. Unit switching converts populated dimensions and the order increment, clears the displayed result, and requires a fresh calculation in the selected units.

Worked imperial example

A rectangular pit is 6 ft long, 6 ft wide, and 5 ft deep, filled with stone at a supplier-confirmed void ratio of 0.35.

  1. Area: 6 × 6 = 36 ft².
  2. Gross volume: 36 × 5 = 180 ft³.
  3. Gross volume in cubic yards: 180 ÷ 27 = 6.667 yd³.
  4. Effective storage: 180 × 0.35 = 63 ft³.
  5. Storage in gallons: 63 × 7.48052 = 471.3 gal.

Measured result: 180 ft³ gross, 63 ft³ or 471.3 gallons of storage. The stone order is the gross volume, 6.667 yd³ unrounded, or 7 yd³ when rounded up to a 1 yd³ supplier increment. Ordering 63 ft³ of stone would under-order by nearly two thirds, because that number is the water space, not the stone.

Worked metric example

A rectangular pit is 2.0 m long, 2.0 m wide, and 1.5 m deep, at a void ratio of 0.35.

  1. Area: 2.0 × 2.0 = 4 m².
  2. Gross volume: 4 × 1.5 = 6.0 m³.
  3. Effective storage: 6.0 × 0.35 = 2.1 m³.
  4. Storage in litres: 2.1 × 1,000 = 2,100 L.

Measured result: 6.0 m³ gross, 2.1 m³ or 2,100 litres of storage, and a 6.0 m³ loose stone order before any supplier increment rounding.

How much does the void ratio change the answer?

More than most pits allow for. Take the imperial pit above, 180 ft³ gross, and change only the ratio.

Void ratioEffective storageStorage in gallons
0.3054 ft³403.9 gal
0.3563 ft³471.3 gal
0.4072 ft³538.6 gal

The stone order does not change in this table, because the order is the gross volume in every row. Only the storage changes. Record the ratio, its product, and its source beside the result so a later reviewer can see which assumption moved.

What does this calculator not do?

The calculator measures quantity for a pit you already have. It does not decide whether that pit is big enough, suitable, or legal for your site.

ConditionWhy one run does not fitQuantity action
Prefabricated chamberCapacity is a manufacturer-stated figure, not pit geometryUse the stated capacity, plus surround voids from the dry well volume methods guide
Chamber in a gravel surroundChamber body displaces stoneAdd chamber capacity to surround gross × void ratio, with the chamber footprint deducted
Irregular, sloped-wall, or stepped pitCross-section is not constantSplit into uniform sections and add unrounded volumes
Pipe or fitting inside the pitIt displaces stone and storage spaceMeasure a separate deduction when the occupied length is material
Drainage sizingRainfall, contributing area, soil infiltration, and groundwater decide adequacyUse a drainage design from the responsible designer or authority
Soil suitability, setbacks, water-table clearance, and permitsLocal rules and site conditions governCheck the project record and local requirements before digging

A quantity result does not make an excavation safe. Locate and control underground installations before digging. In the United States, contact 811 a few business days before digging so utilities are marked.

Common dry well volume mistakes

The common dry well volume mistakes guide explains each of these errors with its project consequence.

  • Using gross pit volume as the storage number.
  • Ordering the storage volume as if it were the stone quantity.
  • Using one fixed void ratio for every stone product and condition.
  • Entering radius in the diameter field.
  • Using one average depth across abrupt changes.
  • Including a soil cap or cover depth in the stone pit depth.
  • Computing a chamber from outside dimensions instead of its stated capacity.
  • Rounding every section before adding the product total.
  • Treating a quantity result as proof of drainage sizing, soil suitability, or excavation safety.

What should a dry well quantity record include?

  • Project, pit, drawing, and revision identifiers.
  • Shape, section limits, dimensions, depth readings, and units.
  • Gross pit volume before any ratio is applied.
  • Stone product, void ratio, ratio source, and date.
  • Effective storage in cubic feet or cubic metres, plus gallons or litres.
  • Selling unit, minimum order, increment, rounded order, and quote date.
  • Separate chamber, pipe, surround, backfill, spoil, and restoration calculations.
  • Design, utility, excavation, delivery, access, and unresolved checks.

Sources and scope

Source scope: NIST supports the stated conversions. Number Analytics supports the typical void-ratio range only; the project value must come from the supplier or project record. PMC supports the chamber-geometry limitation. Project drawings, specifications, surveys, supplier records, soil and groundwater information, local rules, and responsible people control the product, depth, material state, order, and work plan.

Review note: Calculation logic and independent automated fixtures passed internal review. Saleem Sial is the research and editorial owner. Waseem Sial's external review remains ongoing. The published page is indexable.